How to Build a Cabinet Schedule for a Bangkok Apartment Project
A room-by-room cabinet schedule helps Bangkok apartment buyers compare built-in furniture quotes, approve sample units and organise site delivery.
Before issuing a request for quotations for built-in cabinets, give every supplier the same list of apartments, drawings and items. A quote based on the number of apartments alone conceals whether kitchen, entry, bedroom and bathroom units are included for every layout. A cabinet schedule makes the differences visible before a supplier prices materials, hardware or site work.
99 Points records the SKV64 project in Bangkok as an apartment development of 938 units. Its published product scope lists shoe cabinets, kitchen cabinets, wardrobes and vanity cabinets, and its page records delivery in August 2024. The case shows the range of cabinet categories a single apartment project can involve. For a new development, the project team can use that range as a starting point and build its own schedule from the measured layouts and current contract drawings. 99 Points SKV64 project record
Build the schedule from the apartment register
Start with a plan or register that maps every apartment number to a type and a drawing revision. Make separate schedule lines for the kitchen cabinet run, each wardrobe, the entry shoe cabinet and the vanity, where included. Each line needs an item identifier, an apartment type, a per-unit quantity, a drawing reference and a finish or hardware reference. Where several rooms use compatible parts, identify those shared components in the item detail while keeping the room allocation clear.
The quantity column should represent the number of units that actually receive an item. For example, a hypothetical stock schedule might show 20 units of Type A and six of Type B, with one kitchen set in each. If Type B has an extra bedroom wardrobe, that wardrobe belongs on the Type B schedule even if the kitchen can be quoted against the same detail. The buyer can then trace the extra requirement to the correct six apartments and compare bids on the same basis.
An apartment count can include units outside the present order or layouts that have yet to be released. Use a status at the unit or schedule-line level so the figure for the quotation is distinguishable from the quantity approved for production. A supplier that has priced a provisional apartment can then update its affected line when the layout is confirmed. Procurement can compare revisions without rebuilding the whole estimate.
Decide which mirrored layouts deserve a separate line
A mirrored apartment may need a separate item identifier when holes, hardware, finish or service access change how a part is made. The same cabinet schedule can keep verified common items together and list left- or right-hand parts separately. See also checking mirrored apartment cabinet drawings.
Use a documented field check before a supplier relies on dimensions that depend on the building. ANSI/AWI 1232-2022, a US industry standard for manufactured wood casework, includes field verification when applicable. AWI's separate submittal requirements describe casework drawings in plan, elevation and section with construction dimensions and provision for field dimensions. These references give buyers a practical way to frame requests. The applicable requirements on a Bangkok project come from the project's own contract and governing rules. AWI manufactured wood casework requirements · AWI casework drawing requirements
Use the sample to release a defined group of work
Before the review, give the manufacturer, design team and contractor the same schedule revision. In the sample apartment, open the cabinet doors and drawers through their full travel. Check available access around the sink and appliance connections. Read exposed panels and edge details against the finish sample in the project's agreed viewing conditions. If the installation team had to add a filler or move a bracket, record the change on the relevant drawing and say which other apartments it affects.
The signed record should identify the approved drawing and the items released. Record open questions separately. For instance, the kitchen fronts can be accepted while the bathroom vanity on a revised service wall remains awaiting measurement. When the mismatch is fixed, update the affected item and confirm which apartments have already been made or packed under the earlier revision. This gives the factory a release it can act on and the buyer a record against which to check the order on arrival.
Compare the factory price and the site price on separate lines
Ask each bidder to identify its included materials, hardware, factory assembly and packing. Use separate lines for freight, unloading, distribution to individual apartments, installation, damage checks and replacements. Where an installer will adapt to uneven walls or floors, name who supplies the extra parts and who signs off any change to dimensions. Record the point at which the site team accepts the cartons and the point at which the completed item is accepted.
For example, one quote may include cartons grouped by floor and another may price delivery to the building entrance. They support different site plans even where the catalogue finish and cabinet price agree. Ask for a sample packing label and match it to the cabinet ID on the room schedule. The person receiving the shipment should be able to tell where it goes and which revision governs it before opening the carton.
A buyer preparing a quote request can send the apartment register, the incoming drawing revisions and the item schedule as one package. Mark which items are ready for pricing, which depend on field measurements and where the bidder must identify an exclusion. Approve the sample against the same schedule used for the quote. That gives the team a practical record from comparable bids to site acceptance.