99 Points · · Updated
How to approve and inspect wood finishes for hotel casegoods across multiple properties
A procurement guide to finish submittals, mock-up room checks and batch release for hotel casegoods on UAE hospitality projects.
A headboard can look right in the mock-up room while the wardrobe beside it reads noticeably darker. If several properties share a finish, agree the acceptable range on physical samples and identify the components that need a closer match in the same sightline. Put both requirements in the finish schedule before releasing the casegoods package.
On 2 November 2026, IHG announced that Yas World Resort on Abu Dhabi’s Yas Island had joined Vignette Collection, bringing six hotels together in one resort. For procurement teams planning a multi-property fit-out with shared finishes, the practical question is how to keep approvals consistent when each property has its own room types, lighting and delivery programme.
Approve a range the factory can reproduce
Ask the supplier for a finish submittal on the proposed production substrate. For stained veneer, submit a set that shows the target and acceptable lighter and darker examples, with representative grain. Include the finish code, veneer and grain direction, substrate, stain or coating system, sheen and revision. Have the contract’s designated approver sign the physical control set, and retain matching sets with the project team and production team. The AWI requirements for finish samples are a useful reference when setting up the submittal because they address production-representative material, sample identification and the expected grain and colour range.
Mark the faces that will be seen together on the shop drawings. A pair of wardrobe doors or a bank of drawers may need a closer visual match than two items installed in separate rooms. Where veneer, solid timber lippings and laminate are intended to coordinate, review them side by side before approving the finish package.
Agree how the match will be checked
Use the agreed lighting and viewing conditions for the factory inspection. During mock-up sign-off, check the finishes under the intended guestroom lighting or an agreed equivalent. Compare the pieces in their installed orientation and record the conditions. This matters when different substrates or coatings appear to match under one light source and diverge under another. The ASTM D1729 approach to visual colour appraisal sets out a method for opaque materials under diffuse illumination. Use it where appropriate to agree a repeatable comparison, then record the lighting and viewing conditions for the actual room.
If the specification calls for instrumental colour measurements, agree the colour-difference formula, illumination and measurement conditions, reading locations and tolerances for the relevant surfaces. Compare the readings with the approved visual range at the sample stage. Grain, texture, sheen and where the pieces sit in the room can affect what an acceptable match looks like.
Hold suspect batches before they leave the factory
Inspect first-off pieces against the control set before the main run, then follow the agreed batch inspection plan. Record the finish code and revision, production lot, item and room-type reference, inspector and release decision. Agree when material, stain or coating changes trigger a fresh submittal.
If a batch falls outside the signed range, hold the affected pieces and compare them with the retained samples under the agreed conditions. When replacing a single door or drawer front, inspect it beside its matching set before release. That check keeps a passing sample from becoming a visibly mismatched installation.
Carry the sample reference through to snagging and replacements
For a hotel purchase order, 99 Points recommends distinguishing items that must match as a set from items accepted anywhere within the signed finish range. For a pair of wardrobe doors, put the matching-set ID on the packing labels alongside the property, room, handing and approved sample revision. The team receiving a second shipment can then see which pieces belong together and what was approved.
On the inspection sheet, record whether the inspector released the pieces, held them for reinspection or requested a written concession. Identify the person who can approve an exception and the date a decision is needed. A photo tied to the original room and lot helps identify the issue. The replacement decision comes from comparing the relevant physical pieces in the agreed conditions.
Procurement questions
What colour tolerance should I specify for stained hotel casegoods?
Agree it using production-representative samples and the way each item will be seen in the completed room. If the contract uses instrument readings, specify the applicable surfaces, formula, measuring conditions, reading locations and limits. Adjacent doors can have a tighter matching requirement than furniture installed in different rooms.
Can we approve a factory shipment from photos?
Use photos to document the item, finish code, batch and any discrepancy. For release, use the inspection method agreed in the contract and compare with the physical control set. An appointed inspector can carry out the comparison on site when the procurement team is working remotely.
How do we colour-match a replacement wardrobe door for a room already in use?
Locate the original lot and sample revision. Then compare the replacement alongside the retained door under the agreed viewing conditions. If the old finish has changed in service or the batch is no longer available, ask the project team to approve a matched pair when a single replacement falls outside the visual range.